So much of what you can find online about architecture relates to the finished appearance of a building, but architects on the job need to know how to develop the design intent and document and convey that intent to bidders and builders. This blog is intended to prompt constructive discussion about the architectural processes of making buildings through making drawings and specifications for builders to follow and through administering contracts for construction.
School Construction Photo
A FEW WORDS OF CAUTION
A FEW WORDS OF CAUTION ABOUT THE CONTENT ON THIS SITE:
The content provided on this site and in the Posts is intended to be thought-provoking, educational, and - in some cases - entertaining. It is not intended as direction or recommendations for the design or construction of any specific building project. The information is provided in good faith but without assurance as to its completeness, accuracy, or suitability for any particular purpose. If you are considering using information provided on this site, you are responsible for verifying its appropriateness to your needs, and you assume all risk for its use.
The content provided on this site and in the Posts is intended to be thought-provoking, educational, and - in some cases - entertaining. It is not intended as direction or recommendations for the design or construction of any specific building project. The information is provided in good faith but without assurance as to its completeness, accuracy, or suitability for any particular purpose. If you are considering using information provided on this site, you are responsible for verifying its appropriateness to your needs, and you assume all risk for its use.
Tuesday, November 22, 2011
Planning for Concealed Site Conditions
Discovery of concealed site conditions can raise havoc with a project, possibly disrupting the construction schedule and adversely impacting the project budget. Here's a link to an article I wrote a few years ago to share some of my experience with concealed site conditions: Planning for Concealed Site Conditions
Thursday, September 29, 2011
Value Engineering
Any discussion of value engineering (V.E.) is likely to produce a rush of criticisms of the process if you work in an architecture or engineering practice. The architects and engineers are likely to recall bad experiences when V.E. was started late, approaching or following the completion of construction documents, at a time when the project schedule did not allow sufficient time to fully consider consequences and implement V.E. changes in a comprehensive and well coordinated manner. They are likely to complain that "V.E. stripped the value out of the project."
A better approach to V.E. is to start it earlier, when material and system decisions are being formulated and before a lot of time is invested in developing applicable details and specifications.
The Whole Building Design Guide (http://www.wbdg.org/resources/value_engineering.php) offers an excellent synopsis of V.E. and a clear picture of the advantages of doing it earlier in the life of a project.
A better approach to V.E. is to start it earlier, when material and system decisions are being formulated and before a lot of time is invested in developing applicable details and specifications.
The Whole Building Design Guide (http://www.wbdg.org/resources/value_engineering.php) offers an excellent synopsis of V.E. and a clear picture of the advantages of doing it earlier in the life of a project.