School Construction Photo

School Construction Photo
A job site photo of a school under construction

A FEW WORDS OF CAUTION

A FEW WORDS OF CAUTION ABOUT THE CONTENT ON THIS SITE:
The content provided on this site and in the Posts is intended to be thought-provoking, educational, and - in some cases - entertaining. It is not intended as direction or recommendations for the design or construction of any specific building project. The information is provided in good faith but without assurance as to its completeness, accuracy, or suitability for any particular purpose. If you are considering using information provided on this site, you are responsible for verifying its appropriateness to your needs, and you assume all risk for its use.

Tuesday, November 22, 2011

Planning for Concealed Site Conditions

Discovery of concealed site conditions can raise havoc with a project, possibly disrupting the construction schedule and adversely impacting the project budget. Here's a link to an article I wrote a few years ago to share some of my experience with concealed site conditions: Planning for Concealed Site Conditions

Thursday, September 29, 2011

Value Engineering

Any discussion of value engineering (V.E.) is likely to produce a rush of criticisms of the process if you work in an architecture or engineering practice. The architects and engineers are likely to recall bad experiences when V.E. was started late, approaching or following the completion of construction documents, at a time when the project schedule did not allow sufficient time to fully consider consequences and implement V.E. changes in a comprehensive and well coordinated manner. They are likely to complain that "V.E. stripped the value out of the project."

A better approach to V.E. is to start it earlier, when material and system decisions are being formulated and before a lot of time is invested in developing applicable details and specifications.

The Whole Building Design Guide (http://www.wbdg.org/resources/value_engineering.php) offers an excellent synopsis of V.E. and a clear picture of the advantages of doing it earlier in the life of a project.

Tuesday, December 1, 2009

"By Others" and "N.I.C."

The terms "By Others" and "Not In Contract" (or "N.I.C.") can add confusion to construction documents if the intent of the terms is not well established within the documents. The note "By Others" on a drawing may be intended to indicate that an item is to be provided by a different trade under the same overall construction contract, and "N.I.C." may be intended similarly to indicate an item that is to be provided by a different trade. However, these notes may have different meanings for different readers. Without further clarification, a general contractor seeing a note "By Others" or "N.I.C." may take it at face value to mean the item is not part of the general contractor's scope at all, even if the intent of the note was to indicate its exclusion only from the work of a particular trade or subtrade or a particular bid package. It is better to develop and use terms that convey the intent more precisely. For example, if an item shown on a site plan is intended to be provided by an electrical contractor whose work scope is also established on other drawings, it may be appropriate for the site plan to include the term "By Electrical Contractor" in a note relating to the item. Alternatively, it may be practical for all items that are not intended to be part of the site work to be noted "Not by Site Work Contractor", provided the term does not contradict a general contractor's contractual authority to assign such work. Drawings which are specifically intended to describe the work of a particular trade or subtrade can benefit from a List of Abbreviations or a List of Terms which clarify the meaning of such notes in order to minimize confusion.

Wednesday, November 4, 2009

Reviewing the Contractor's Application for Payment

On most public construction projects, the Architect reviews the Contractor's monthly Applications for Payment (a.k.a. "Requisitions") and certifies the amount to be paid to the Contractor for that month. If the Application is made on AIA Document G702, the front page includes the names of the Project, the Owner, the Contractor, and the Architect, an Application number, date(s) indicating the period covered by the Application, an overview accounting of the monetary status of the construction project, starting with the original contract sum and including a calculation of the Current Payment Due, considering change orders, the total amount completed and stored to date, Retainage to be withheld, and previous certificates for payment. The front page also includes a Change Order Summary, certification by the Contractor, conditions (terms) of certification by the Architect, and the amount certified. Continuation sheets should break down the contract sum and progress according to the approved Schedule of Values (see The Schedule of Values deserves close attention) and also include a detailed accounting of the status of work on approved Change Orders.

The Architect should review even the basic information on the front page before looking at the detailed information on the continuation sheets. It helps to have a copy of the previous month's Application in hand for comparison. Once you determine that the current month's Application is for the appropriate project (seriously), check the Original Contract Sum. In more than one instance, a contractor has changed the Original Contract Sum on an Application for Payment, resulting in an increase in payment without an approved Change Order. The Original Contract Sum should remain the same for the life of the Contract. Before turning to the continuation sheets, the Architect should apply the same scrutiny to the rest of the front page calculations and the wording of the certification. Different certification language may carry different liability.

Detailed information on the continuation sheets is typically generated as part of a "pencil requisition" process and in anticipation of work to be completed by the end of the month. The Architect needs to consider whether the final Application for the month represents work that was actually accomplished by the end of the month. If the Architect is aware that an anticipated material delivery did not occur, then the Architect should not certify payment for that. Likewise, if the Architect is aware that a specific work item was not completed, then the Architect should not certifiy payment as if the item had been completed. Necessary adjustments to the continuation sheets must be carried over to the front page and to the overall amount certified by the Architect for the period covered by the Application. It may be practical for the Contractor to make the necessary adjustments and then resubmit a corrected Application for the Architect's certification. If timely payment is an overriding concern, then the Architect may need to make the adjustments by annotating the Application, certifying a reduced amount, and notifying both the Owner and the Contractor of the reasons for the adjustments. (See also It takes timely money to make a project go )

Sunday, November 1, 2009

Manage Design Costs with Early Project Overtime

One of Mike's PM tips for managing design costs on a project: "If you know you are going to have to work overtime on a project," he said, "do it in the beginning. It costs less to do overtime when there are only one or two people working on a project." (See Purposeful chaos (the 2-minute design offense))

This makes a lot of sense when considering a project on a compressed time line. If you're trying to figure out how to get all the work done in a short period of time, the least attractive alternative is having an army of designers and drafters burning the midnight oil and generating design questions as the completion deadline approaches. Eleventh hour overtime can quickly burn through budgeted hours and fee dollars, and too many new or unanswered questions at that stage can lead to unplanned chaos.

It's also interesting to consider how this principle of early overtime might benefit progress and labor costs on a construction site. Early trades - like earthwork, concrete, and steel - set the stage for a larger work force, and trades can multiply as the project becomes ready for their work.

Thursday, October 29, 2009

Shop Drawing Review Comments

While it can be frustrating for an architect to review shop drawing submittals that appear to lack adequate preparation or attention to contract requirements, it is still important for the architect to maintain professional decorum in the review comments. This is equally true for the review of resubmitted shop drawings that do not include corrections noted by the architect on a previous submittal. An inadequate resubmittal may warrant separate correspondence from the architect to the contractor noting the repeated deficiencies and, if applicable, the possibility of adverse effects on the project schedule; but the review comments and correspondence should communicate clearly and without sarcasm or accusations. For example, "Why can't you get it?" is not a proper architect review comment on a shop drawing submittal.

Friday, May 22, 2009

Construction Documents Coordination Matrix



It may look a little "geeky", but this matrix can be an effective tool for considering interdisciplinary coordination needs. The design disciplines for a project are listed across the top and down one side. The intersection points represent coordination between disciplines (e.g., between Civil/Site and Electrical). Seeing the possibilities in this format can help to minimize coordination gaps. On a given project, the extent and specifics of coordination will differ from point to point, and the design displines may also differ. Still, seeing an intersection point can prompt thoughts about needed coordination between any two disciplines. For example, where Civil/Site meets Foodservice, it may bring to mind the need to coordinate the locations of exterior condensing units with site work. Etc. Etc. Etc
.

Looking at this coordination matrix, it is also easy to see how extensive coordination really is (and must be) on an architectural project. On some complex projects, coordination can be seen as a full time job in itself, from the coordination of consulting agreement scopes of work to the coordination of sub-trade scopes of work and the dotting of i's and crossing of t's in construction documents.